J-2026-0405
Ozzyslat feature fence 34m + double swing gate, Bowral home
← All custom jobs
J-2026-0405 Quality Check
Ozzyslat feature fence 34m + double swing gate, Bowral home
Customer: Marcus & Elena Whitmore Branch: ACT — Queanbeyan Range: Ozzyslat Horizontal Slat™ · Woodland Grey
Contract value
$12,840
+ GST $1,284.00 = $14,124.00 inc
Job workflow
- ✓ Deposit
- ✓ Design
- ✓ Fab
- ✓ Powder
- 5 QA
- 6 Install
- 7 Complete
- 8 Invoiced
Live job costing
42% margin| Materials (Colorbond, steel, hardware) | $4,006.80 |
| Powder coat | $964.60 |
| Factory labour (cut, fab, weld) | $1,484.00 |
| Delivery & install | $964.60 |
| Total cost | $7,420.00 |
| Contract (ex-GST) | $12,840.00 |
| Gross margin | $5,420.00 · 42.2% |
Assigned
- Estimator
- Ellie Vasquez
- CAD / design
- Anh Pham
- Install lead
- Josh Carmody
Key dates
- Booked
- 25 June 2026
- Install due
- 21 July 2026
- Deposit
- Paid
Lead time
9 working daysGenerated from job complexity — expected days to manufacture.
- Fencing base build+8d
- Scope & length+1d
Expected build 9 working days
Linked records
- Direct job (no quote)
- Production floor →
- Marcus & Elena Whitmore · COD