J-2026-0385
Ozzyslat 28m + Louvre privacy screen 9m², Stanhope Gdns
← All custom jobs
J-2026-0385 Quality Check
Ozzyslat 28m + Louvre privacy screen 9m², Stanhope Gdns
Customer: Aisha & Omar Haddad Branch: Sydney — Minchinbury Range: Ozzyslat Horizontal Slat™ · Monument
Contract value
$7,450
+ GST $745.00 = $8,195.00 inc
Job workflow
- ✓ Deposit
- ✓ Design
- ✓ Fab
- ✓ Powder
- 5 QA
- 6 Install
- 7 Complete
- 8 Invoiced
Live job costing
41% margin| Materials (Colorbond, steel, hardware) | $2,365.20 |
| Powder coat | $569.40 |
| Factory labour (cut, fab, weld) | $876.00 |
| Delivery & install | $569.40 |
| Total cost | $4,380.00 |
| Contract (ex-GST) | $7,450.00 |
| Gross margin | $3,070.00 · 41.2% |
Assigned
- Estimator
- Priya Nair
- CAD / design
- Anh Pham
- Install lead
- Kane Mitchell
Key dates
- Booked
- 26 June 2026
- Install due
- 22 July 2026
- Deposit
- Paid
Lead time
8 working daysGenerated from job complexity — expected days to manufacture.
- Fencing base build+8d
Expected build 8 working days
Linked records
- Direct job (no quote)
- Production floor →
- Aisha & Omar Haddad · COD