J-2026-0374 CAD & Design Rush

Winten North Ryde — 72m Blade + glass balustrade 18m

Customer: Winten Property Group Branch: Sydney — Minchinbury Range: Blade Range™ · Monument

Contract value

$16,200

+ GST $1,620.00 = $17,820.00 inc

Job workflow

  1. Deposit
  2. 2 Design
  3. 3 Fab
  4. 4 Powder
  5. 5 QA
  6. 6 Install
  7. 7 Complete
  8. 8 Invoiced

Live job costing

35% margin
Materials (Colorbond, steel, hardware) $5,713.20
Powder coat $1,375.40
Factory labour (cut, fab, weld) $2,116.00
Delivery & install $1,375.40
Total cost $10,580.00
Contract (ex-GST) $16,200.00
Gross margin $5,620.00 · 34.7%

Assigned

Estimator
Priya Nair
CAD / design
Anh Pham
Install lead
Kane Mitchell

Key dates

Booked
09 July 2026
Install due
27 July 2026
Deposit
Paid

Lead time

7 working days

Generated from job complexity — expected days to manufacture.

  • Fencing base build+8d
  • Scope & length+2d
  • Rush — expedited (−30%)×0.7
Expected build 7 working days